Hillside foundations in Los Angeles: how the ground, the report and the City shape what gets built
California Contractor License #1160113, Class B (General Building)
Last updated November 26, 2026.
Quick answer
On a hillside lot, the ground report comes before the foundation design. In the City of Los Angeles, on hillside grading work a licensed soils engineer and a licensed engineering geologist explore the lot unless LADBS waives it, the Grading Division reviews their report, and the engineers design the foundation from it. Importing or exporting more than 1,000 cubic yards of soil in a Hillside Grading Area adds a public hearing. We accept high-complexity hillside jobs. Planning a hillside project? Call (909) 486-3818.
This page is for owners and investors weighing a sloped lot. Whatever goes on top, a townhome group, an apartment building or a hillside ADU, the ground, the water and the rules shape a slope foundation, and the engineers design it for the building it carries.
Why a slope needs a different foundation
On a slope the foundation question is about the soil above, below and beside the building, not only under it. LADBS requires a geology and/or soils report when Los Angeles Building Code (LABC) section 7006.2 or 1803 applies, and its Grading Division approves it. On hillside grading work, a licensed soils engineer (a registered civil engineer practicing soils engineering, or GE) and a licensed engineering geologist (a CEG) do the exploration unless LADBS waives it. The reports address:
- Slope stability. Analysis is called for on slopes steeper than 2:1 or with adverse geology. LADBS sets minimum factors of safety of 1.5 for permanent slopes, 1.25 for temporary and 1.0 for seismic.
- Settlement. Analysis is called for where differential settlement would exceed 1/4 inch.
- Wall pressures. Walls over 6 feet, walls with a surcharge and walls in adverse geology need a soils investigation.
- Mapped hazards. Landslide, liquefaction and fault hazards, debris flow (LABC 7014.3), and the bulking and shrinkage percentages for the earth moved.
Footings on or near slopes steeper than 1:3 follow California Building Code (CBC) section 1808.7. LADBS treats code setbacks as sufficient only when the report has addressed stability, erosion, drainage and debris flow.
Who decides. The GE and the CEG recommend. A structural engineer designs the foundation members. A civil engineer designs grading and drainage. The Grading Division approves the reports. The builder builds what the approved plans show.
The usual systems
- Piles and drilled shafts (caissons). CBC section 1810.1.1 bases the design on the geotechnical investigation. Depth and bearing material come from the GE and the CEG.
- Retaining walls. Up to 6 feet, LADBS allows the code table when the wall supports certified compacted fill or undisturbed native earth with no adverse geology.
- Soldier piles with lagging, and tiebacks. The Caltrans Trenching and Shoring Manual (2011), which is highway practice and not Los Angeles code, describes a cantilever soldier pile wall as relying on passive ground resistance, economical to about 18 feet. Braced or anchored walls are built top down and are economical to about 80 feet.
- Shoring. LADBS requires a stability analysis for temporary excavations over 5 feet vertical, surcharged by off-site structures, slot cuts, or in adverse geology.
- Subdrains, backdrains and waterproofing. Subdrains must eliminate hydrostatic pressure, or the wall is designed for it over its full height. CBC section 1805 requires below-grade walls and floors to be waterproofed or dampproofed.
The Los Angeles rules a hillside project meets
Two hillside maps
The City Planning Hillside Area (Baseline Hillside Ordinance) is not the Hillside Grading Area of LABC section 7003 (Bureau of Engineering Map A-13372), where the haul route hearing applies. Check both for the lot.
The Baseline Hillside Ordinance
LAMC 12.21 C.10, as amended by Ordinance 184,802 (effective March 17, 2017), governs new buildings, additions and major remodels on R1, R1H, RS, RE or RA lots in the Hillside Area. It limits setbacks, floor area (lower on steeper slope bands), height, coverage, parking and grading. Cut plus fill is capped at 1,000 cubic yards plus a number of cubic yards equal to 10 percent of the lot area in square feet (a 5,000 square foot lot: 1,500 cubic yards), never above the zone maximum. Exemptions include cut and fill for piles and caissons that involve no freestanding retaining walls, driveway cut and fill up to 500 cubic yards, and remedial grading the Grading Division approved on a geotechnical report. A Hillside Construction Regulation district caps grading at 6,000 cubic yards. For a lot in any other zone, including multi-family zones, ask City Planning which hillside limits apply.
The grading permit and the haul route hearing
A grading permit is required for grading, import and export, except the LABC 106.1.2 exceptions such as a cut under 2 feet. Hillside pile and caisson excavation under permitted buildings is excepted. For import or export over 1,000 cubic yards in a Hillside Grading Area, LAMC 91.7006.7.5 calls for a public hearing. The application needs the Grading Division's report approval letter, haul route and environmental questionnaires, and a vicinity map with an owner list. A Street Services fee and a Bureau of Engineering bond follow.
Report review and deputy inspection
The Grading Division acts on a report as approved, approved with conditions, or not approved. LADBS Information Bulletin P/BC 2026-113 states no age limit for a report, so ask the Division. LABC 1704.2 requires a registered deputy inspector for certain hillside grading and foundation earthwork. The deputy confirms setbacks were approved before piles or walls start and flags soil conditions that differ from the report.
What drives cost and time
We give no dollar figures here. These items move cost and schedule:
- Report cycles: two licensees explore, then the reports are reviewed and corrected.
- Depth to competent material and groundwater, which drive pile length and dewatering.
- Import or export: over 1,000 cubic yards adds the hearing, the bond, route limits and the 12 and 18 month clocks.
- Grading caps and the paperwork for exemptions.
- Neighbors: the 30-day notice and surcharge from nearby buildings.
- Mapped seismic hazard zones, erosion control from October 1 to April 15 for grading over 200 cubic yards, and drainage design with its inspections.
Five questions to ask before you buy a hillside lot
- What soils and geology reports exist at LADBS for this lot and its neighbors, how old are they, and approved with what conditions?
- Is the lot in a Seismic Hazard Zone, an Alquist-Priolo zone or a City fault study area, and what investigation follows?
- What do the GE and the CEG say about slopes steeper than 2:1 on or above the lot, landslides, bedding, fill and seeps?
- How many cubic yards are cut, filled, imported and exported, on what kind of street, against the 1,000 cubic yard hearing line and the zone cap?
- Where does the water go, and what stands next to the excavation?
If you are buying the lot, read buying a hillside lot in Los Angeles.
How we work on a hillside job
We accept high-complexity hillside jobs and build from plans the building department has approved. The designers and licensed engineers the project requires prepare the plans, and licensed professionals prepare the ground reports. We do not take grading, shoring or retaining walls as stand-alone jobs; they are part of the building project we contract to build. We give no opinion on your ground. Read how we work as a hillside contractor in Los Angeles, or see our multi-unit construction.
Questions owners ask
Who decides what foundation a hillside lot needs?
The soils engineer (GE) and the engineering geologist (CEG) recommend, a structural engineer designs the foundation members, and a civil engineer designs grading and drainage. The LADBS Grading Division approves the reports. A contractor builds what the approved plans show.
When does moving soil off a hillside lot need a public hearing?
Importing or exporting more than 1,000 cubic yards in a Hillside Grading Area needs a hearing before the Board of Building and Safety Commissioners (LAMC 91.7006.7.5). The grading permit must be obtained within 12 months of Board approval and hauling must start within 18 months, or a new application and hearing are required.
Do I have to notify the neighbor before excavating next to their property?
LABC section 3307.1 calls for 30 days' written notice when the excavation is deeper than both the neighbor's foundation and its distance from the line. No permit issues without evidence of the notice. Civil Code section 832 separately requires reasonable notice of any excavation, and 30 days for a neighbor to protect an endangered building.
Sources
- LADBS Information Bulletin P/BC 2026-113, geology and soils reports, listed in the LADBS bulletin index.
- LADBS Information Bulletin P/BC 2026-068, hillside work rules; P/BC 2026-049, slope stability evaluation; P/BC 2026-001, footing and building setback from slopes; P/BC 2026-060, 30-day notification; P/BC 2026-128, permits and inspections.
- LADBS P/BC 2023-139, remedial grading exempted from the Baseline Hillside Ordinance, and P/BC 2023-034, registered deputy inspectors.
- LADBS haul route forms: import and export application (July 2018) and haul route clearance procedure (July 25, 2018).
- City Planning, Hillside Single Family Zones checklist CP-4061 (February 14, 2020), and Baseline Hillside Ordinance correction sheet 107A (April 6, 2017).
- 2025 California Building Code, chapter 18, soils and foundations; Caltrans, Trenching and Shoring Manual (2011), section 4.1; Los Angeles County Code, Title 22 and Title 26.
Note. EMC Development Solutions Corp is a private building contractor, California Contractor License #1160113, Class B (General Building). This page is general information, not a publication of the City of Los Angeles or any agency, and it is not legal or engineering advice. We do not prepare plans or ground reports, and we give no opinion on your ground. The rules above are for the City of Los Angeles, and do not bind outside it: unincorporated Los Angeles County has its own grading code (Title 26 Appendix J) and slope rules (Title 22 chapter 22.104). They are under the 2026 Los Angeles Building Code on the 2025 California Building Code, effective January 1, 2026. The Baseline Hillside Ordinance grading figures come from a City Planning checklist dated February 14, 2020, the City's new zoning code is phasing in, and the haul route forms date from 2018, so numbers and forms may have changed. Sources checked November 2026. Check with LADBS and City Planning before you rely on any of it.
Learn about our multi-unit construction and how we take on hillside construction in Los Angeles, or contact us about your project.
Planning a hillside project? Call (909) 486-3818.
Call (909) 486-3818