Building a custom home in Los Angeles: the path from lot to certificate of occupancy
California Contractor License #1160113, Class B (General Building)
Last updated November 23, 2026.
Quick answer
A complex custom home in Los Angeles follows a path the City sets: the design, a ground report where the lot is a hillside, plan check in rounds, permits, then site work, foundation, frame and systems under inspection, and a final inspection. We take on custom homes on hillside lots and other difficult sites, including homes with pools or elevators, and we build from plans the building department has approved. Planning a custom home? Call (909) 486-3818.
This page is for owners building a custom house in Los Angeles County and for the architects who design them: hillside lots, pools, elevators, tight streets and other difficult sites. It shows the path of the work, what a hillside adds below ground, who answers for what, and where jobs stall. The pictures are diagrams, because the order of the work and the people it depends on do not show in a photograph of a finished house.
It names what exists and why it matters, and links the agency. It does not replace your architect, your engineers or the City, who answer for your lot.
The path from lot to certificate of occupancy
From lot to certificate of occupancy
No City document gives one sequence for every lot, so read the figure as a common order and not as a schedule. In a Hillside Grading Area, the City's grading plan check sheet says no grading permit can be issued before the building permit. Retaining walls, shoring and pools are separate applications, each with its own plan check.
Look up the lot before anything else. The City's ZIMAS property profile shows the zoning and the overlays on a parcel, and NavigateLA carries the Hillside Referral Report where one applies. Whether a particular rule reaches your lot is for the City to say, on the parcel.
Once the permit is issued, a hillside or custom home typically takes 1 to 1.5 years to build, not counting delays caused by the City. The design, the ground report and plan check come before that, and their length depends on the lot and the City. The same range, with its caveats, is on the hillside contractor page.
What a hillside lot adds below ground
On a slope the question is the soil above, below and beside the house, not just under it. A licensed soils engineer and a licensed engineering geologist explore the lot and write the reports, the LADBS Grading Division reviews them, and the engineers design the foundation from them. Figure 2 is a simplified section.
A simplified hillside section
- Caissons or piles. Drilled shafts that carry the building down to firm material. The ground report recommends the depth and the bearing material.
- Grade beam. A concrete beam that ties the tops of the shafts together under the house.
- Retaining wall. It holds back the uphill soil. Walls over 6 feet high, walls carrying extra load and walls in adverse geology need a soils investigation report.
- Waterproofing. Basement walls and slabs are waterproofed with an approved waterproofing product.
- Subdrain. A perforated pipe behind the wall that carries water to an approved outlet. Subdrains must eliminate hydrostatic pressure, or the wall is designed to resist it over its full height.
Where the water goes is its own question. In a Hillside Grading Area, the City does not allow storm water infiltration unless it is clearly shown that the water cannot affect the stability of slopes, and that showing is a geotechnical engineer's to make. For the soils report, the usual foundation systems and the City's grading rules, read hillside foundations in Los Angeles. If an ADU is part of the plan, see building a hillside ADU in Los Angeles.
Who answers for what
A custom home is a team job, and each member answers for one part. The builder builds what the approved plans show. The builder does not design the home, write the ground reports or give an opinion on the ground.
Who answers for what
The City is several offices. LADBS reviews plans and ground reports and inspects the work. Depending on the lot, City Planning, the Bureau of Engineering and the Fire Department each clear their own part.
Where custom home jobs stall, and what restarts them
The stalls the City's own documents describe are mostly in the paper: a street width, a notice, a hearing, a report that the plans do not match. Figure 4 names five so you can ask about them before you buy a lot or hire a team. The street rule, for one, is the Bureau of Engineering's and a Zoning Administrator's to apply to your parcel, and a road widening is a civil engineer's design.
Where custom home jobs stall
If a build has already stalled, read my contractor left the job unfinished.
How we work on a custom home
We take on complex custom homes: hillside lots, homes with pools or elevators, and other difficult sites. Before we accept a job we review the owner's plans. We judge fit on plans that are 90 to 100 percent complete, on the reports the lot needs, and on how the owner wants the job to run and the timeline. Then we issue a written proposal that names the work the plans show, with exclusions and assumptions. The scope is in writing before any number appears, every job is priced in a written proposal and a signed contract before work begins, and the contract states the approximate start and completion dates. Work starts after the permit is issued.
We do not draw plans, prepare ground reports or give an opinion on your ground. We do not take grading, shoring or retaining walls as stand-alone jobs. They are part of the building project we contract to build, carried out by licensed subcontractors under our contract. If you do not yet have a design team, we know designers, architects and engineers across Southern California and can introduce you to one. Architects and owners call the same number.
For how we work on slopes, see hillside construction in Los Angeles, and for the paper behind a job, how we work, in six steps. For a look at plan check from the inside, read Nine units, five years, Erick Chung's own account of a ground-up nine-unit building he contracted before the Corp held its license, where plan check came back for corrections five times. The Corp did not contract or build that job, and it was not a hillside or custom home. More about the person behind the Corp is under About.
Questions owners and architects ask
Who designs a custom home, and what does the builder do?
The owner's architect designs the home and the engineers design its parts: a structural or civil engineer the foundation members and retaining walls, a civil engineer grading and drainage. The City reviews and approves the plans. The builder builds what the approved plans show, and does not prepare plans or ground reports.
Does a hillside custom home need a ground report?
On hillside grading work in the City of Los Angeles, a licensed soils engineer and a licensed engineering geologist explore the lot unless LADBS waives it, and the Grading Division reviews their report. The foundation is then designed from it. Whether your lot needs one is for the City and your engineers to say.
Which comes first on a hillside lot, the building permit or the grading permit?
In a Hillside Grading Area, the City's grading plan check sheet says no grading permit can be issued before the building permit. Whether your lot is in a Hillside Grading Area is for the City to answer, on the parcel.
How long does a custom home take to build?
Once the permit is issued, a hillside or custom home typically takes 1 to 1.5 years to build, not counting delays caused by the City. The design, the ground report and plan check come before the permit, and their length depends on the lot and the City, so no figure is given for them here. Conditions found once work begins and changes made during the job can add time.
Sources
- LADBS Grading Division plan check sheet CL-BC-2026-003 (revised April 24, 2026): the building permit before the grading permit in a Hillside Grading Area, separate applications for retaining walls, shoring and pools, and the eight week minimum for a haul route hearing.
- LADBS Information Bulletin P/BC 2026-068, hillside work rules: exploration by a licensed soils engineer and a licensed engineering geologist unless waived. P/BC 2026-113, contents of reports: retaining walls over 6 feet, with surcharge or in adverse geology, and subdrains. P/BC 2026-118, storm water infiltration in the Hillside Grading Area.
- LADBS IB-BC-2026-003, 30-day notice before excavation, and P/BC 2026-134, haul route applications, with the 12 and 18 month clocks.
- City Planning, Hillside Single Family Zones checklist CP-4061 (February 14, 2020), on street access, and the Bureau of Engineering Permit Manual, pages 05 (Hillside Referral Form Preparation) and 09 (Street(s) Along Lot Frontage(s) Minimum 20' Wide).
- Los Angeles Fire Department, Hydrants and Access.
Note. EMC Development Solutions Corp is a private building contractor, California Contractor License #1160113, Class B (General Building). This page is general information, not a publication of the City of Los Angeles or any agency, and it is not legal or engineering advice. We do not prepare plans or ground reports, and we give no opinion on your ground. The diagrams are simplified and typical, for illustration; your architect and engineers design your home and sign its plans. The rules named here are the City of Los Angeles's. Other cities and unincorporated Los Angeles County have their own, and the street access rule comes from a City Planning checklist dated February 14, 2020, so numbers and forms may have changed. The build time is a typical range, not a promise for any job. Sources checked November 2026. Check with the City before you rely on any of it.