Nine units, five years
Erick Chung’s own work, before EMC Development Solutions Corp held its license.
In February 2020 I contracted with the owners to build a nine-unit townhouse building in the Compton area of Los Angeles County. I was the general contractor myself, before EMC Development Solutions Corp, where I work now, was licensed. The Corp did not contract or build this job. My contract was weeks old when the pandemic began.
The project had an earlier approval, and it had lapsed. In May 2020 the county told me that the plot plan, the building application and the planning approval had all expired. The old building also had to be tested for asbestos. The stucco and the siding tested positive, which meant a notice to the air-quality district before the work could start. Demolition came first, then grading, while planning and the building plans went back through the county. Planning approved the plans in September 2020. The grading permit issued that December.
I uploaded the first set for building plan check in September 2020. It came back for corrections five times before it was cleared in October 2021, and I worked each round with the engineers and the county’s reviewers. When I needed to process plan check and job compliance, the county’s public counters had shut their doors. The work moved onto the county’s online permit system, EPIC-LA, and I had to learn how that system worked as I went. The closed offices and the new system slowed the administrative side of the job. Even after the offices reopened in the fall of 2021, a county office was still warning that pandemic email volume would slow its replies. The building permit issued in December 2021, about fifteen months after the first upload.
The lumber had been priced before the pandemic. In November 2021 I sent the same list back out to be priced again at that year’s prices. The steel contractor came on in January 2022. By the summer of 2023 the building was framed and the stucco was finished. Late in the job the electrical service had to change from single-phase to three-phase, after the equipment had been ordered for single-phase. The electrical plans were revised for three-phase service and went back through the county in 2023. The street improvements ran on their own permit. Its site plan expired in January 2024 and had to be restamped, and that permit issued in March 2024.
In December 2024, near the end, the site was hit by theft and vandalism. Final-stage inspections followed in January.
When this job got hard, I did not step back. I kept working, and I kept talking to the owners, until the building was done. I do not hide behind a contract. I care about the building and the people I build it for.
The certificate of occupancy is dated February 2025. I sent it to the owners with a short note: “What a journey.”
A certificate of occupancy closes the permit. I still care how that building does.