ADU sewer availability clearance in Los Angeles: what the City checks, who decides, and what to ask
California Contractor License #1160113, Class B (General Building)
Last updated November 9, 2026.
Quick answer
In the City of Los Angeles, an ADU permit application needs a "sewer availability" clearance from the Bureau of Engineering. The Bureau's own manual says a "Pending" status means "there is more work to be done by the Applicant," so ask the department what it is waiting for. This page describes the City of Los Angeles only. Planning an ADU? Call (909) 486-3818.
Other cities and Los Angeles County have their own sewer agencies and rules. Ask yours. A clearance that is still open at another department, such as sewer or utility capacity, is among the causes listed on an expired or stalled ADU permit.
What is the sewer availability clearance?
A clearance is an approval from another City department. The City's bulletin on converting an existing building to an ADU or junior ADU, Information Bulletin P/BC 2026-150 (revised August 13, 2026), says in section VI: "Approval from BOE is required for all ADUs and JADUs for the following:" It lists first: "Assessment of sewer capacity and availability (i.e., 'sewer availability' clearance)." BOE is the Los Angeles Department of Public Works, Bureau of Engineering. The City's bulletin on unpermitted units under AB 2533, P/BC 2026-161 (revised September 2, 2026), says the same.
The Bureau's permit manual page "05 - Sewer Availability" (Revised on 07-03-2025) describes how the Bureau handles this clearance on a building permit application.
What does the Bureau check first?
The manual tells Bureau staff to confirm that the sewer "Must be adjacent to the lot," and says: "Confirm the property is within <200 feet from the mainline. There may be no sewer adjacent to the property or, even if there is, it may not be available for a variety of reasons."
What do the clearance statuses mean?
The manual lists the statuses the Bureau gives the clearance. In its words:
- "Pending - This status means there is more work to be done by the Applicant as BOE can not provide a final approval"
- "Denied - No Sewer available or the Applicant does not want to perform the required conditions"
- "Approved - Applicant has met BOE requirements and no additional BOE permits are required"
- "Approved with Conditions - Applicant has met the initial requirements at the present time, but may have other conditions to meet later in the construction process. Applicant must complete the conditions in order for Certificate of Occupancy to be granted."
If the clearance reads "Pending," the City's own definition says there is more for the applicant to do. Ask the department what it is waiting for, and get the answer in writing.
When does LA Sanitation review the capacity?
The Bureau's manual page "01 - S-Permit Processing Procedures" (Revised on 05-18-2026) describes a Sewer Capacity Availability Request, or SCAR: "Used when there is an anticipated significant increase in sewer discharge." It says: "The BOE District office will be able to approve the request without a SCAR if ALL the following are true:"
- "Discharge is less than 3,000 GPD"
- "No Industrial Waste Permit required"
- "No sewer ejector"
- "No groundwater or stormwater discharge"
It continues: "If any of the above conditions are not met, the SCAR will be sent to Sanitation for review." Ask the department whether a capacity review applies to your unit.
What if no sewer is available?
The manual says: "If connection to a sewer line is not available, the applicant will need to either build a sewer line or to obtain approval from LADBS for an Onsite Wastewater Treatment System (OWTS)."
State law has two lines on this. Government Code section 66314(d)(9) lists "Approval by the local health officer where a private sewage disposal system is being used, if required." Section 66323(f) says: "A local agency may require, as part of the application for a permit to create an accessory dwelling unit connected to an onsite wastewater treatment system, a percolation test completed within the last five years, or, if the percolation test has been recertified, within the last 10 years."
Who decides whether my ADU has to connect?
The manual says the Bureau does not decide whether a connection is required, with an exception for the Hillside Ordinance. It says: "In general, LADBS has the authority to make the determination whether or not an Applicant has to connect." Ask the department which applies to your unit.
What does state law say about a separate utility connection?
Government Code section 66311.5(d) covers the units described in section 66323(a)(1), such as a unit created within existing space. For those units it says a local agency, special district, or water corporation "shall not require the applicant to install a new or separate utility connection directly between the unit and the utility ... unless the unit was constructed with a new single-family dwelling, or upon separate conveyance of the accessory dwelling unit pursuant to Section 66342." For how conversions work, see can I convert my garage into an ADU.
For any other ADU, section 66311.5(e) says: "For an accessory dwelling unit that is not described in paragraph (1) of subdivision (a) of Section 66323, a local agency, special district, or water corporation may require a new or separate utility connection directly between the accessory dwelling unit and the utility."
For water, sewer or power service, state law says a junior ADU is not counted as a separate or new dwelling unit (section 66338(a)). A local agency may also designate where ADUs may be permitted. Section 66314(a) says: "The designation of areas may be based on the adequacy of water and sewer services and the impact of accessory dwelling units on traffic flow and public safety."
Who decides, and what should I ask?
The Bureau of Engineering signs the clearance, LA Sanitation reviews capacity when a SCAR is needed, and, in general, LADBS decides whether a connection is required. Your department can tell you where your file stands. Ask the department what the sewer clearance is waiting for. Ask whether a capacity review by LA Sanitation is needed. Ask whether your unit counts as a conversion inside existing space. Get each answer in writing. For the other clearances, see can I convert my garage into an ADU. For what else can hold a file, see an expired or stalled ADU permit, what drives the cost of building an ADU and finishing a half-built ADU.
Where does EMC fit?
EMC Development Solutions Corp is a building contractor. Once your plans are approved and the permit is issued, we can contract to build the ADU. Work starts only after the permit is issued.
This is how we work. We walk the project with you and tell you plainly what the work involves and what could go wrong. The scope comes in writing, with the exclusions and assumptions, before any number appears. Every job is priced in a written proposal and a signed contract before work begins. When we build a project, the building inspections, through final, are part of the construction contract. We do not prepare plans. They come from the owner's designer, architect or engineer. We will tell you on the first call whether the job is a fit.
EMC Development Solutions Corp is a private building contractor. This page is general information. It is not a publication of the City of Los Angeles, Los Angeles County or the State of California, and it is not legal advice. Law and department rules as of November 2026. Check with your building department before you rely on any of it.
Sources, read November 9, 2026: Government Code sections 66311.5, 66314, 66323 and 66338, from the Legislative Counsel's public text of the California codes; LADBS Information Bulletin P/BC 2026-150, revised August 13, 2026, and P/BC 2026-161, revised September 2, 2026; City of Los Angeles Bureau of Engineering permit manual, 05 - Sewer Availability (Revised on 07-03-2025) and 01 - S-Permit Processing Procedures (Revised on 05-18-2026).